Heavily reinforced strip foundations for BFW warehouse within Sizewell C

COMMERCIAL CONSTRUCTION PROJECT AT BFW WAREHOUSE BUILDING, SIZEWELL C FOR VOLKER FITZPATRICK

Project Description


Heavily reinforced strip foundations for BFW warehouse within Sizewell C


Client: Volker Fitzpatrick

Start date: April 2026

Completion Date: May 2026 (6-week programme)

Value: £555k
 

Project Details


  • Foundations – reinforcement and mesh
  • Fix only holding down bolts
  • Pouring 1300m3 readymix concrete in 4 separate pours
  • Using a bespoke deigned formwork system
  • Appropriately resourced to achieve a challenging 6 week programme
PDF Download
DOWNLOAD THIS
PAGE AS A PDF
TALK TO US ABOUT YOUR NEXT PROJECT
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
 
Previous
 
© Copyright AD Bly Construction 2026