COMMERCIAL CONSTRUCTION PROJECT AT BFW WAREHOUSE BUILDING, SIZEWELL C FOR VOLKER FITZPATRICK
Project Description
Heavily reinforced strip foundations for BFW warehouse within Sizewell C
Client: Volker Fitzpatrick
Start date: April 2026
Completion Date: May 2026 (6-week programme)
Value: £555k
Project Details
- Foundations – reinforcement and mesh
- Fix only holding down bolts
- Pouring 1300m3 readymix concrete in 4 separate pours
- Using a bespoke deigned formwork system
- Appropriately resourced to achieve a challenging 6 week programme